  "version": "1.0.0",
  "currency": "USD",
  "scale": "dollars",
  "scope": "Five synthetic cost codes for a scalar forecast, with no customer or project data.",
  "cases": [
    { "code": "110", "label": "Site work", "budget": 320000, "committed": 240000, "billed": 160000, "ap": 30000, "closed": false, "expectedCtc": 160000, "expectedFinal": 320000 },
    { "code": "210", "label": "Structure", "budget": 500000, "committed": 545000, "billed": 340000, "ap": 55000, "closed": false, "expectedCtc": 205000, "expectedFinal": 545000 },
    { "code": "320", "label": "Design signoff complete", "budget": 125000, "committed": 100000, "billed": 80000, "ap": 5000, "closed": true, "expectedCtc": 20000, "expectedFinal": 100000 },
    { "code": "410", "label": "Finishes billed past commitment", "budget": 150000, "committed": 90000, "billed": 110000, "ap": 12000, "closed": false, "expectedCtc": 40000, "expectedFinal": 150000 },
    { "code": "510", "label": "Unbudgeted utilities", "budget": 0, "committed": 16000, "billed": 6000, "ap": 6000, "closed": false, "expectedCtc": 10000, "expectedFinal": 16000 }
  ],
  "expectedTotals": { "budget": 1095000, "billed": 696000, "ctc": 435000, "projectedFinal": 1131000 },
  "conventions": [
    "Billed costs are already incurred and are included only once in estimated final cost.",
    "Open commitments are committed minus billed, floored at zero.",
    "Remaining uncommitted budget is budget minus the greater of committed or billed, floored at zero. It is zero after an explicitly completed milestone.",
    "Accounts payable is included in billed. Cash due dates and lender draw timing are outside this fixture."
  ]
}