How to forecast a cash shortfall before a construction draw
Start with cash available to the project. Put contractor payments on their due dates and the lender draw on its expected receipt date. Run the schedule again with a later receipt date. The lowest balance shows how much cash you could be short before funding arrives.
What happens when the draw arrives late?
In this hypothetical example, the developer opens May with $90,000 and expects a $150,000 lender draw. The three payment due dates are the same in both scenarios.
| Date | Cash event | Expected draw | Delayed draw |
|---|---|---|---|
| Opening cash | $90,000 | $90,000 | |
| Early trade invoices ($60,000) | $30,000 | $30,000 | |
| Draw arrives in the expected case | $180,000 | $30,000 | |
| Contractor payment ($75,000) | $105,000 | -$45,000 | |
| Utilities and site costs ($20,000) | $85,000 | -$65,000 | |
| Draw arrives in the delayed case | $85,000 | $85,000 |
Both scenarios end with $85,000. With the delay, the forecast first goes negative on May 14 and the gap reaches $65,000 before the draw arrives. The negative forecast is a funding gap under the stated payment schedule.
Build the forecast for your project
- Start with the cash actually available to pay this project’s bills. Keep restricted funds separate.
- Use the dates cash is due out. Include known invoices, retainage when due, and other scheduled payments.
- Log the submission date, remaining approval steps, and expected receipt date for each draw.
- Calculate the running balance after each event, then move the receipt date to test a delay. Review same-day inflows and outflows in the order they could clear.
- Record the first shortfall date and the largest gap. Update the forecast as payments clear and lender timing changes.
Connect the cash forecast to the project budget
A cost-to-complete forecast estimates how much remains to be spent. The cash schedule shows when those payments and lender receipts affect available cash.