Construction cost-to-complete benchmark
Try this five-line budget in your spreadsheet or project software. The reference forecast is $1,131,000 against a budget of $1,095,000.
Cellect AI ran this synthetic calculation on . The benchmark covers line-level arithmetic in a local run of Fi’s scalar engine.
Download the example
The data covers a normal open cost code, a commitment above budget, a completed milestone, billing above commitment and a cost with no budget.
How to calculate the reference
- Subtract bills to date from commitments. Floor the open commitment at zero.
- For open scope, subtract the greater of commitments or bills to date from the budget, and floor the remaining uncommitted amount at zero. For the completed milestone, set the uncommitted amount to zero and keep any open commitment.
- Add those two remaining amounts for cost to complete. Add bills to date for the estimated final cost.
Accounts payable is already part of bills to date. The fixture uses whole US dollars. Payment due dates and lender draw timing require a separate cash schedule. See how a delayed draw can create a cash shortfall.
Results on the same inputs
| Calculation | Cost codes matched | Estimated final cost | Absolute line errors |
|---|---|---|---|
| Fi scalar engine | 5 of 5 | $1,131,000 | $0 |
| Unused budget only | 2 of 5 | $1,101,000 | $80,000 |
| Open commitments only | 3 of 5 | $1,011,000 | $120,000 |
The unused-budget shortcut missed the overcommitted structure work and unbudgeted utilities. It also kept an unneeded allowance for the completed milestone. Those errors partly offset in the project total. The open-commitment shortcut missed the remaining uncommitted scope.
The unused-budget method subtracts billed cost from the budget. The open-commitment method subtracts it from committed cost. Both floor the result at zero. Absolute line errors sum the absolute differences from the reference across the five codes.